Project Completion - Birkbeck Primary School

We are delighted to have now handed over the completed project to Birkbeck Primary school. The expansion works commenced on site in August 2018 and enables the school to increase capacity from a 2 Form Entry (FE) to a 3 FE school.

With the project won via a competitive tender process, a key factor in ensuring the success of the project was the delivery strategy for the works. The construction works on site were delivered in four phases, with extensive site logistics plans and detailed construction programmes produced to ensure the highest levels of safety standards were achieved within the live school environment.

Phase 1:
  • Demolition of single storey block
  • Installation of temporary parking area.
  • Demolition of existing library & erection of new library
  • Internal ground & first floor alterations
Phase 2:
  • Erection of new 2-storey extension
  • Kitchen extension and associated
  • Landscaping
Phase 3:
  • Demolition of remainder of single storey block and hall corridor, erection of new hall corridor,
  • Landscaping to central courtyard & carpark
  • Conversion of existing ground floor classroom to studio space.
  • Erection of link walkway/canopy
Phase 4:
  • Alterations to existing ground floor hall
  • Internal ground/first floor alterations
  • Landscaping to car parking areas to front and side of building

Birkbeck School has said about the works:

'Many thanks to Bexley LA for securing the project funding for us and managing it throughout and a massive thank you to WWMartin builders who have been awesome throughout.'