Contract Award - Birkbeck Primary School
After a competitive tender period, we are very happy to have been awarded the contract to expand Birbeck Primary School from a 2 Form Entry (FE) to a 3 FE school.
The works will be completed in a live school environment and extensive preparations have been made to ensure the safety of all school users and to minimise disruption.
The expansion works have been planned to be delivered in four phases:
Phase 1:
- Demolition of single storey block
- Installation of temporary parking area.
- Demolition of existing library & erection of new library
- Internal ground & first floor alterations
Phase 2:
- Erection of new 2-storey extension
- Kitchen extension and associated
- Landscaping
Phase 3:
- Demolition of remainder of single storey block and hall corridor, erection of new hall corridor,
- Landscaping to central courtyard & carpark
- Conversion of existing ground floor classroom to studio space.
- Erection of link walkway/canopy
Phase 4:
- Alterations to existing ground floor hall
- Internal ground/first floor alterations
- Landscaping to car parking areas to front and side of building