Project Progress - Cottington Road, Cliffsend

As shown in the photos, excellent progress has been made on site as all of the timber frame structures to the 41no. houses on the North site are now complete.

This significant milestone follows the completion of the Section 278 works earlier this year, and with all timber frame structures complete on this portion of the site, other key stages of work will continue to progress at pace.

In regards to the South site, the main construction works to this part of the development have been awaiting the completion of all archaeological investigative works, which we are pleased to say are now complete.

The foundation works to a dozen of the new homes is progressing and the next few months will see our sister company WWM Civils progress the remaining foundation works for the rest of the properties. The first of the timber frame structures has also commenced and a clear sequence is being followed as works continue.

Latest LINKEDIN POSTS
Contact Us
Quick Enquiry
©2024 WWMartin. Site by Dan Patching Creative Design.

Registered Company Name: WW Martin Ltd. Registered Office: Dane Park Road, Ramsgate, Kent, CT11 7LT. Company Registration No. 504927. Place of Registration: England