We are pleased to share progress at our Sir Geoffrey Leigh Academy project for Kent County Council.

Construction is progressing well, with the main steel frame now complete and precast hollow-core slabs installed at first-floor and roof level. We are currently progressing the installation of structural toppings to these areas, alongside below-ground drainage works and the formation of the ground-floor slab.

Following completion of these works, the project will move into the next phase, with façade and roofing installations commencing.

The development will deliver a new standalone sixth form building, supporting the academy's 2FE expansion and providing dedicated teaching and social spaces for sixth form students.

Client: Kent County Council
Architect: Clague Architects
Engineers: Evans & Langford
Consultant: Fusion Project Management